Who this checklist is for

I'm the office administrator at a mid-sized contracting firm. I manage all facilities and jobsite material ordering—roughly $180K annually across eight vendors. If you're the person who signs off on a brick order, a concrete block delivery, a pallet of tile adhesive, or an LVL beam shipment, this checklist is for you.

I'm not a project manager. I don't run crews. But I'm the one who gets the call when the wrong block shows up, or when finance rejects an invoice because the paperwork doesn't match the PO. Over four years and 400+ POs, I've distilled this into nine steps. Every one of them exists because I skipped it once.

Step 1: Confirm the spec sheet, not the product name

Never order "standard brick" or "standard block." Those phrases mean different things to a masonry contractor, a distributor's inside sales rep, and a freight dispatcher—and the difference can be 3/8 of an inch.

Ask for the actual spec: nominal vs. actual dimensions, compressive strength (psi), absorption rate, and for concrete block, whether it's lightweight or normal weight. For tile adhesive, confirm whether it's thin-set or medium-bed, and what ANSI classification applies (A118.4 for modified, A118.1 for unmodified).

This is the single biggest source of rework I see. The first time I ordered block for a foundation job, I wrote "8x8x16 CMU." The vendor shipped lightweight. The engineer needed normal weight. We ate a restocking fee and a two-day delay.

Step 2: Get the lead time — in writing, in days, not weeks

"Two to three weeks" is not a lead time. It's a range designed to survive the vendor's production queue. What most people don't realize is that "standard turnaround" often includes buffer the vendor uses to manage scheduling. It's not necessarily how long your order takes.

Ask specifically: "If I place this order by 10 a.m. Tuesday, what date does it leave your dock?" Then write down the answer and the rep's name. When I stopped accepting vague windows and started documenting quoted dates, our late-delivery disputes dropped from roughly once a month to once a quarter.

5 minutes of verification beats 5 days of correction. I've learned that lesson every way you can, including the hard one.

Step 3: Verify invoicing before you verify price

This one is non-negotiable. I learned it the expensive way in 2023: I found a great price on a pallet of tile adhesive—about $40/unit cheaper than our regular distributor. Ordered 60 units. They couldn't provide a proper invoice (handwritten receipt only). Finance rejected the expense report. I ate $620 out of the department budget because I didn't ask one question upfront.

So now, before I place any order with a new vendor, I ask:

  • Can you send me a sample invoice with your tax ID and remit-to address?
  • Do you support net-30 terms, or is this prepay-only?
  • Do you match PO numbers on the invoice, or do I have to reconcile manually?

If a vendor can't answer those three questions in an email, that's a red flag about how the rest of the relationship will go (I really should've known that from the start).

Step 4: Confirm the loadout condition — not just the delivery address

Nobody asks about this until the truck is stuck. You need to confirm three things with every bulk brick, block, or LVL shipment:

  1. Truck type — flatbed, boom, or box truck? Can your site accommodate it?
  2. Unloading responsibility — does the driver handle it, or do you need a forklift on-site at a specific time?
  3. Site access — gravel, tight turns, low overhead lines, weight restrictions on the road?

We once had a block delivery arrive with the wrong truck for a site with a narrow residential street. The driver refused to go in (fair—he'd have gotten stuck). We paid a second delivery fee plus driver wait time.

Step 5: Batch-match before you split shipments

If your order is coming in multiple deliveries, ask the manufacturer to pull from a single production batch. This matters especially for brick and tile adhesive. Two batches of "the same" brick can look visibly different side by side—color tone, surface texture, edge sharpness.

For tile adhesive, batch variance is a real problem. Different production lots can behave differently on cure time and open time, which matters on large-format tile installs.

I learned this the day after a client pointed out a visible color seam across a facade. Our vendor had shipped three separate batches. The fix cost more than the original material.

Step 6: For LVL beams, verify depth availability and moisture content

LVL beam orders have their own checklist. Before you buy, confirm:

  • Depth and length — these come in specific dimensions; "we have it in stock" means nothing without depth and length confirmation.
  • Moisture content — manufacturers mark it; if the rep can't tell you, ask for the mill certification.
  • Bearing details — width matters, especially when the beam sits on a 2x4 or 2x6 wall.

An LVL beam distributor who can't send you the mill cert within a day is probably brokering, not stocking. There's a real difference, and it shows up on delivery day.

Step 7: Lock in the price with a written quote and expiration date

Verbal quotes are useful for budgeting. They are not useful for ordering. Get a written quote with:

  • Unit price, per-unit quantity, and total
  • Delivery cost (included or not)
  • Price expiration
  • Minimum order quantity if applicable

Here's something vendors won't tell you: the first quote is almost never the final price for an ongoing relationship. There's usually room to negotiate once you've proven you pay on time. But you can't negotiate against a verbal number—you need the paper trail.

Step 8: Confirm the receiving contact and time window

This sounds obvious. It isn't. Your vendor's dispatch team has a schedule. Your site contact has a lunch break. If those two don't sync, your brick pallet sits on the truck for two hours (and you get billed for it).

Every order now goes out with a named receiving contact, a cell number, and a 4-hour delivery window that's confirmed by both sides. We were losing roughly $400/month in driver wait fees before I locked this down.

Step 9: Do a final read-back before you hit send

The last step is the cheapest and the one most people skip. Before placing the order, read your own PO back to yourself as if you were the vendor:

  • Did I list the right product spec?
  • Is the quantity what I actually need?
  • Is the ship-to address right?
  • Did I include the PO number they need to match?
  • Did I put the receiving contact on it?

This last step has caught more mistakes than any other item on this list. I don't always get it right (who does), but this one step has saved me at least five bad orders.

Things that still trip people up

Underestimating breakout. When a brick or block pallet is split across multiple deliveries, breakout counts are your responsibility. Confirm each partial shipment count on the BOL, or you'll be reconciling shortages three weeks later.

Assuming "in stock" means ready to ship. In-stock inventory still has to be picked, staged, and dispatched. Ask for a dock date, not a stock status.

Forgetting that tile adhesive ships with temperature guidance. Some modified mortars become unusable if they freeze during transit. If you're ordering in winter, ask about the shipping method.

FTC guidelines on advertising and substantiation apply to how vendors present their products—but they don't protect you from a poorly-written PO. That part is on you (and me, and everyone else who clicks "submit" at 4:47 p.m. on a Friday).

The checklist above takes maybe 15 minutes to run. The average rework cost I've logged from a skipped step is closer to two days and several hundred dollars. Do the math once and you'll keep the list.

Share WhatsApp
Stefan Petrescu
Stefan Petrescu

Stefan Petrescu is a building climate-systems analyst specializing in air-conditioning equipment, heat pumps, ventilation units, ductwork, controls, boilers, fireplaces, stoves, and flue components. He uses ANSI/ASHRAE Standard 62.1-2025 ventilation criteria while comparing outdoor-air rate, airflow, static pressure, heating and cooling capacity, part-load efficiency, sound level, filtration, condensate control, combustion-air provision, and clearances. His application guides help mechanical engineers, installers, and owners size systems, verify interfaces, and balance comfort, indoor air quality, energy use, and serviceability.